Downtime

Power turned off due to lightning strikes

Feb 08 at 12:56pm AEDT
Affected services
Redpoint GitLab
Redpoint ID
License Manager
EventHost
Metrics
Error Reporting

Resolved
Feb 09 at 03:18am AEDT

Services are now online again.

Updated
Feb 09 at 02:43am AEDT

The power company has yet again delayed the time of the on-site investigation, now expected to occur by 8:00am. However, they have reported that voltage levels have been normal over the last 6 hours according to remote monitoring, so we are turning on the main breaker in the hope that no further outages will occur.

Updated
Feb 08 at 08:50pm AEDT

The power company has provided an updated estimate of 2:30am Melbourne time.

Updated
Feb 08 at 05:33pm AEDT

Estimated time of resolution is currently 9pm Melbourne time.

Updated
Feb 08 at 04:00pm AEDT

There is a power brownout following the earlier lightning strikes. We are waiting on the power company to confirm that power has been properly restored before turning on the main breaker

Updated
Feb 08 at 01:28pm AEDT

Power has been restored

Created
Feb 08 at 12:56pm AEDT

Power is currently turned off at the main breaker due to lightning strikes causing intermittent power outages and the potential for power surges. Power will be turned on again once the storm has passed.